Sign Up for Updates

 

Construction Updates

Weekly Look Ahead

Construction Update Week of

For the week of , the following construction activities will be taking place:

 

Construction activities anticipated for this week include start of Runway 08-26 grooving as well as continuation of testing and commissioning for the GRE facility.  The testing is required as part of the GRE design-build contractor’s contract with PortsToronto. As discussed with stakeholders, the public, and the City of Toronto during the Development Review & Approval Process, noise testing will be conducted both within and on the outside of the GRE facility as per the design-builder’s design requirements airside (on the island), as this will ensure the performance and testing criteria are met.

 

 Link to the City of Toronto's webpage on the approval process can be found at www.toronto.ca/grereview

 