Event Date
Award of Construction Contract May 13, 2016
Contractor Mobilization Start May 19, 2016
Start of Major Construction Activities Week of June 13, 2016
Runway 15-33 Conversion to Temporary Taxiway Echo October 12, 2016
Anticipated barging operations (2017 season) May 1, 2017 - July 21, 2017
Runway 08-26 Completion of Work November 5, 2016
Runway 06-24 Completion of Work October 12, 2016
GRE Facility Opening April 19, 2017
Permanent Taxiway Echo Completion of Work July 15, 2017
Apron Widening/Rehabilitation May 28, 2018 - September, 2018
Construction Completion (Substantial Completion) September 1, 2018