Construction Schedule

Event Date
Award of Construction Contract May 13, 2016
Contractor Mobilization Start May 19, 2016
Start of Major Construction Activities Week of June 13, 2016
Runway 08-26 Nightly Closures Start June 15, 2016
Runway 06-24 Day/Night Closure Start June 8, 2016
Runway 15-33 Conversion to Temporary Taxiway Echo October 12, 2016
Start of Barging Operations July 8, 2016
Runway 08-26 Completion of Work November 5, 2016
Runway 06-24 Completion of Work October 12, 2016
GRE Facility Opening March 2017
Taxiway Echo Reconstruction July 28, 2017
Apron Widening/Rehabilitation 2018 Construction Season (TBD)
Construction Completion (approx.) October 2018