Construction Update

Phase 7 (full depth rehabilitation of the main apron) will continue working from west to east.  Approximate 20 m sections of the apron will be rehabilitated each night and returned to service in the morning.  Re-establishment of base course asphalt over the complete Phase 7 area will be carried out during the later part of the week, followed by placement of surface course asphalt and pavement markings.  Contractor demobilization will commence as well in some areas which will involve daytime barging operations.

Weekly Look Ahead

For the week of , the following construction activities will be taking place:

Completion of surface course asphalt and associated line painting will be ongoing this week as well as some demobilization activities.