Construction Update

Work on Phase 7 (full depth rehabilitation of the main apron) will continue working from west to east.  Approximate 20 m sections of the apron will be rehabilitated each night and returned to service in the morning.

Weekly Look Ahead

For the week of , the following construction activities will be taking place:

The work on Phase 7 (full depth rehabilitation of the main apron) will continue from west to east throughout the week. Approximate 20 m sections of the apron will be rehabilitated each night and returned to service in the morning.